Blog

Steel Framing is Complete

Thursday was a big day for Lever Homes -- we received and erected the steel beams that will support the upper two levels of 1118 - the one bedroom studio.   Things went very smoothly, with all of the pieces fitting into place perfectly in about half of the time we expected.  A few finishing welds on Monday will put the trickiest structural stuff behind us - a necessary move to maximize room on site for parking and private yards. We should be wrapping up framing within the next couple of weeks, so expect to see windows before long. 

Taylor Callaway